Verifiable Administrative Investigations

Dossiers.

Documentary reconstructions of records, resolutions, funding, and public contracts of the Municipality of Atri. Every question is anchored to a public document, line by line.

10
Public works · Access to records

The staircase between Viale Santucci and Vico Marucci: what the documents say

A 19,053.09 euro direct award, the bill of quantities, the Municipality's reply and the technical documents that do not yet appear in the documents consulted. Following councillor Graziosi's request for a check of 2 November 2026.

→
09
Environment · Land · Open data

Atri's land: how much has been covered, and why the course must be reversed

550.74 hectares of artificial surface, 3.43 more in the last year and almost no restoration: the figures of the 2026 ISPRA-SNPA report with their source, how to read them and the records we will ask the Municipality for. With chart and comparison with Copernicus data.

→
08
Heritage · Culture · Civic access

Atri, the museum of donated things: closed for five years, now at the centre of a €350,000 project

Three thousand objects donated by the town, a false ceiling open for five years, a €350,000 project: what the RIABITA sheet says, what it does not say about the collection, eleven questions to the Municipality. With three infographics.

→
07b
School · PNRR · Update

Mambelli school: the promised car park, two funding streams and the questions still open

Final account and inspection, the Conto Termico awarded to the same contractor, how the two funding streams swapped works, the car park offered in the tender as an improvement and the promises missing from the contract. With three infographics.

→
07
School · PNRR · Civic access

Mambelli school: what the Municipality's answer to our civic access request says

The Municipality granted the request and handed over 217 files. The December 2025 variant, works excluded from the PNRR, the technical bid and SAL 6: what the documents show, what is missing, the questions to the Municipality.

→
06
Culture and tourism · Budget

From 2008 to today: €8.6 million for culture and tourism. And the results?

Eighteen years of budgets reconstructed item by item: €8.6 million committed, the 2022 peak explained, a single verifiable public account (the theatre), and no data on visitors or audiences.

→
05
Local finance · Budget

From €3.5 to €12.6 million: what the Court of Audit and the Recovery Plan say

The deficit went from €3.5 to €12.6 million in a year and the Plan runs for fifteen years, to 2039. Act by act: what the documents say, what was said in the chamber, and ten questions to the Municipality.

→
04
Heritage · EU funds

What time does the Licorice Museum in Atri open?

Announced in 2017, funded with European money in 2021, in the title of the works until 2025: what the documents say, and what they don't.

→
03
Territorial reorganisation · Local finance

Merging with Pineto: what actually changes

What the law, Atri's financial recovery plan and Italian precedents really say about a merger with Pineto — and about the "Ager Hadrianus" hinterland alternative.

→
02
School buildings · Sports facilities

The gym that isn't there anymore

From the Bargiglione's collapse in 2012 to the open-air field delivered in 2025: fourteen years without ever giving pupils back a covered gym.

→
01
PNRR · Digital transparency

Atri's cloud was not a "ghost" (corrected dossier)

€121,992 in PNRR funds for 14 municipal services: awarded to Deda Next in 2024, CIG B1B767BE0E, €119,560 settled.

→
00
School buildings · PNRR

Atri's new school: we lined up the records

Two worksites, €5.88 million in cumulative funding, two energy grants on the same building, and a tender over Ferragosto.

→